Our Building Blog
last edited by admin on 22-12-11 (14:36)
20 December 2011

Another big milestone was reached just before Christmas with the installation of the first floor.

 

last edited by admin on 22-12-11 (14:36)
November 2011 - Fantastic Progress

New extension taking shape - the prefabs in the background will be demolished.

Rooms taking shape - to the left of the elavator shaft is the main entrance concourse which will link to the current building.

End of the building nearest existing car gate, picture includes our newest Science Lab (centre)

New pitched roof over existing building - remainder of roof will be completed next Summer.

last edited by admin on 22-12-11 (14:36)
August 2011

New computer network cables

New pitched roof on old building taking shape -3/8/2011

last edited by admin on 22-12-11 (14:36)
8th July 2011

Despite the bad weather, work continues

We will be getting new energy-efficient lights

Recognise the 6th Year social area?

Or the canteen?

Jumble sale or school library?

The new roofs will be completed early in the course of the project

 

last edited by admin on 22-12-11 (14:36)
At last a new beginning

Sr Carmel Gallagher (former Principal), Marita Walton-Lanigan (teacher/Board of Management), Sr Brigid Tunney (Community Leader, Loreto convent & member of BoM), Sarah Dunphy & Sarah Dooley (Head Girls 2011/2012)

Our application to the Department of Education to seek approval for our building programme was first submitted by Sr Carmel in 2000 while the late Helen Renehan had steered the project through the design and planning phase.  So after eleven years of planning and lobbying we were delighted to turn the first sod on 5th July 2011.  This programme involves a complete refurbishment of our existing building as well as a 20,000 square foot extension and will take 15 months to complete.

This is where the extension will go: between our existing building and the Granges Road

This is how our extension will look from the direction of the new medical centre on the Granges Road.

Our flat roofs will be a thing of the past after refurbishment

On 27th of June 2011, the main contractors, McCann Bros, Omagh, arrived.

Before long they were starting to make an impression.  Mary Ward seems to be smiling!

Our heating system is being replaced with a much more energy efficient system.

July 5th, after a busy week, our official ground-breaking ceremony.  Dominic McCann, Marita Walton-Lanigan, Sr Carmel Gallagher, Sr Brigid Tunney, Sarah Dooley, Sarah Dunphy, Colm Keher (Principal), Paul McCann (partially hidden), Martin Hanrahan (Chairman, BoM), Michael Cunningham.  Sr Brigid prayed for the safety of the workers during construction and invoked St. Thomas the patron saint of builders.  Bail o Dhia ar an obair.